Rate riders on an Alberta bill
A rate rider on an Alberta bill is a temporary credit or charge. The UCA says it recovers the actual cost of a service. It can also refund an overcharge. The AUC must approve it before use. The dates on the filed sheet tell you when it applies.
A rate rider is a temporary credit or charge that can appear on electricity and natural gas bills, used to recover the actual cost of providing utility services. It can also refund customers who were overcharged. (from 1 January 2026) [source]
A company that needs a rate rider applies to the Alberta Utilities Commission. A rider is applied to bills for a set period and only after the Commission approves it. (from 1 January 2026) [source] Rate riders are updated monthly, quarterly or annually to reflect the actual cost of providing service for a specific period. (from 1 January 2026) [source]
For the wires and pipes behind these lines, read transmission, distribution and riders.
Electricity riders by distributor
The AUC lists electricity riders by the company that delivers power to your home. Its filed rates give each amount below, with a minus sign for a credit. Town fees vary by area, so those rows show the lowest and highest amounts in force.
Each name links to its row. Dates and decisions come from each amount’s source document. “No end date printed” means that document gives none.
| Name and letter as filed | What it pays for | Amount (residential) | From | To | AUC decision |
|---|---|---|---|---|---|
| 2026 Balancing Pool Allocation Rider | Passes on the Balancing Pool collection or refund received through AESO Rider F. | 0.1290¢ per kWh (from 1 January 2026) [source] a charge. | 1 January 2026 | no end date printed | 30299-D01-2025 |
| TAC Deferral Account Rider Adjustment | Settles the difference between AESO transmission costs and amounts collected from customers. | 0.0483¢ per kWh (1 January 2026 to 31 December 2026) [source] a charge. | 1 January 2026 | 31 December 2026 | 30299-D01-2025 |
| Quarterly TAC Adjustment Rider | Settles transmission costs passed on by the AESO each quarter. | 0.0583¢ per kWh (1 October 2026 to 31 December 2026) [source] a charge. | 1 October 2026 | 31 December 2026 | 31033-D01-2026 |
| Local Access Fee (LAF) | A surcharge imposed by the City of Calgary. Town fee rules. ENMAX Power. | 1.5507¢ per kWh (from 1 January 2025) [source] | 1 January 2025 | no end date printed | City surcharge; no AUC decision listed |
| Name and letter as filed | What it pays for | Amount (residential) | From | To | AUC decision |
|---|---|---|---|---|---|
| Rider G: Balancing Pool Rider | Passes on the Balancing Pool collection or refund received through AESO Rider F. | 0.130¢ per kWh (1 January 2026 to 31 December 2026) [source] a charge. | 1 January 2026 | 31 December 2026 | 30298-D01-2025 |
| Rider J: SAS True-Up Rider | Settles the difference between AESO transmission costs and amounts collected from customers. | -0.016¢ per kWh (1 January 2026 to 31 December 2026) [source] a credit. | 1 January 2026 | 31 December 2026 | 30298-D01-2025 |
| Rider K: Transmission Charge Deferral Account True-Up Rider | Settles transmission costs passed on by the AESO each quarter. | 0.103¢ per kWh (from 1 October 2026) [source] a charge. | 1 October 2026 | no end date printed | 31032-D01-2026 |
| Local Access Fee (Rider LAF) | A surcharge imposed by the City of Edmonton. Town fee rules. EPCOR Distribution. | 1.388¢ per kWh (from 1 January 2026) [source] | 1 January 2026 | no end date printed | City surcharge; no AUC decision listed |
| Name and letter as filed | What it pays for | Amount (residential) | From | To | AUC decision |
|---|---|---|---|---|---|
| Balancing Pool Allocation Rider | Passes on the Balancing Pool collection or refund received through AESO Rider F. | 0.1198¢ per kWh (from 1 January 2026) [source] a charge. | 1 January 2026 | no end date printed | 30274-D01-2025 |
| Base Transmission Adjustment Rider | Adjusts the customer’s base transmission charges by a percentage. | -0.59% (from 1 January 2026) [source] a credit. | 1 January 2026 | 31 December 2026 | 30274-D01-2025 |
| Quarterly Transmission Adjustment Rider (QTAR) | Settles transmission costs passed on by the AESO each quarter. | 0.0155¢ per kWh (1 October 2026 to 31 December 2026) [source] a charge. | 1 October 2026 | 31 December 2026 | 31030-D01-2026 |
| Rider A-1: Municipal Assessment Rider | Rider A-1 passes on municipal assessments for the service area. Town fee rules. FortisAlberta. | -0.68% (from 1 July 2026) [source] to 34.12% (from 1 July 2026) [source] | 1 July 2026 | no end date printed | 30834-D01-2026 |
| Municipal Franchise Fee Rider | Pays the municipality for its electric franchise and use of municipal land. Town fee rules. FortisAlberta. | 0% (from 1 May 2026) [source] to 20% (from 1 January 2013) [source] | Differs by town. See the fee table by town. | no end date printed | 30673-D02-2026 |
| Name and letter as filed | What it pays for | Amount (residential) | From | To | AUC decision |
|---|---|---|---|---|---|
| Rider A: Municipal Assessment | Rider A recovers forecast franchise fees and municipal property taxes. Town fee rules. ATCO Electric. | -0.44% (from 1 April 2026) [source] to 26.21% (from 1 April 2026) [source] | 1 April 2026 | no end date printed | 30657-D01-2026 |
| Rider B: Balancing Pool Adjustment | Passes on the Balancing Pool collection or refund received through AESO Rider F. | 0.133¢ per kWh (1 January 2026 to 31 December 2026) [source] a charge. | 1 January 2026 | 31 December 2026 | 30300-D01-2025 |
| Rider G: Temporary Adjustment | Rider G settles AUC-approved deferral accounts. | -0.212¢ per kWh (1 January 2026 to 31 December 2026) [source] a credit. | 1 January 2026 | 31 December 2026 | 30300-D01-2025 |
| Rider S: SAS Deferral | Rider S settles AESO system access costs each quarter. | 0.068¢ per kWh (1 October 2026 to 31 December 2026) [source] a charge. | 1 October 2026 | 31 December 2026 | 31037-D01-2026 |
A town fee differs by town, so its row shows the lowest and highest amounts and does not give one date. The fee table by town gives the dates and decision for your own town. Use the municipal fee guide for the calculation at your address.
ATCO Gas and Apex household riders
ATCO Gas riders follow the North or South delivery area on your bill, with their purposes listed by the AUC. The tables use the Low Use household rate for ATCO Gas and small general service for Apex. Town fees apply to the charges named in each fee rule, and a row that differs by town points to the fee table by town.
| Name and letter as filed | What it pays for | Amount (residential) | From | To | AUC decision |
|---|---|---|---|---|---|
| Rider A: Municipal Franchise Fee | Rider A pays the municipality for use of its land and the gas franchise. Town fee rules. ATCO Gas North. | 0% (from 1 October 2026) [source] to 35.00% (from 18 December 2024) [source] | Differs by town. See the fee table by town. | Differs by town. See the fee table by town. | 31057-D01-2026, the newest. Each town’s own decision is in the fee table by town. |
| Rider B: Municipal Property Tax | Rider B recovers municipal property taxes on the gas utility’s assets. Town fee rules. ATCO Gas North. | 0% (from 1 October 2026) [source] to 25.70% (from 1 February 2026) [source] | Differs by town. See the fee table by town. | no end date printed | 30911-D01-2026 |
| Rider L: Load Balancing Deferral Account | Rider L refunds or recovers the balance in the load balancing account. | C$0.091 per GJ (1 May 2026 to 31 December 2026) [source] a charge. | 1 May 2026 | 31 December 2026 | 30594-D01-2026 |
| Rider T: Transmission Service Charge | Rider T passes on NOVA Gas Transmission Ltd. transmission charges. | C$1.357 per GJ (from 1 January 2026) [source] a charge. | 1 January 2026 | no end date printed | 30329-D01-2025 |
| Name and letter as filed | What it pays for | Amount (residential) | From | To | AUC decision |
|---|---|---|---|---|---|
| Rider A: Municipal Franchise Fee | Rider A pays the municipality for use of its land and the gas franchise. Town fee rules. ATCO Gas South. | 0% (from 1 September 2026) [source] to 35.00% (from 1 January 2014) [source] | Differs by town. See the fee table by town. | no end date printed | 30949-D01-2026 |
| Rider B: Municipal Property Tax | Rider B recovers municipal property taxes on the gas utility’s assets. Town fee rules. ATCO Gas South. | 0% (from 1 February 2026) [source] to 13.90% (from 1 February 2026) [source] | 1 February 2026 | no end date printed | 30548-D01-2026 |
| Rider L: Load Balancing Deferral Account | Rider L refunds or recovers the balance in the load balancing account. | C$0.091 per GJ (1 May 2026 to 31 December 2026) [source] a charge. | 1 May 2026 | 31 December 2026 | 30594-D01-2026 |
| Rider T: Transmission Service Charge | Rider T passes on NOVA Gas Transmission Ltd. transmission charges. | C$1.357 per GJ (from 1 January 2026) [source] a charge. | 1 January 2026 | no end date printed | 30329-D01-2025 |
| Rider W: Weather Deferral Account | Rider W refunds or recovers weather-related delivery revenue differences. | C$0.325 per GJ (1 September 2026 to 31 December 2026) [source] a charge. | 1 September 2026 | 31 December 2026 | 30876-D01-2026 |
| Name and letter as filed | What it pays for | Amount (residential) | From | To | AUC decision |
|---|---|---|---|---|---|
| Rider A: Franchise Tax Riders | Rider A pays municipal gas franchise fees. Town fee rules. Apex Utilities. | 0% (from 22 September 2026) [source] to 35.00% (from 1 August 2025) [source] | Differs by town. See the fee table by town. | Differs by town. See the fee table by town. | 31073-D01-2026, the newest. Each town’s own decision is in the fee table by town. |
| Rider B: District Property Tax Riders | Rider B recovers district or municipal property taxes on Apex’s assets. Town fee rules. Apex Utilities. | 0% (from 1 April 2026) [source] to 2.8430% (from 1 April 2026) [source] | 1 April 2026 | no end date printed | 30701-D01-2026 |
| Rider B: Municipality-Specific Property Tax Riders | Rider B recovers district or municipal property taxes on Apex’s assets. Town fee rules. Apex Utilities. | 0% (from 1 April 2026) [source] to 7.6404% (from 1 April 2026) [source] | 1 April 2026 | no end date printed | 30701-D01-2026 |
| Rider G: Third-Party Transportation | Rider G pays for moving gas over third-party pipelines. | C$0.869 per GJ (from 1 January 2026) [source] a charge. | 1 January 2026 | no end date printed | 30339-D01-2025 |
| Rider L: Load Balancing Deferral Account Rider | Rider L settles gas delivery and receipt balances and transmission capacity balancing costs. | C$0.172 per GJ (1 May 2025 to 31 October 2026) [source] a charge. | 1 May 2025 | 31 October 2026 | 29699-D01-2025 |
ATCO Gas Riders A and B apply as an addition to delivery charges, including other riders. Apex Rider B also applies as an addition to distribution billings. Its district tax and municipality-specific tax are separate rows.
Calgary’s Method C also uses ATCO Gas South’s Rider E deemed gas value, C$3.15 per GJ (from 1 March 2025) [source], as a fee basis rather than a separate gas purchase.
The balancing pool allocation rider
The balancing pool allocation rider passes on an AESO charge or refund, the AUC says. Each power company shows the amount on its own line, but the same job has different names. The sign of the rate tells you if you pay a charge or get a credit.
The Balancing Pool allocation rider is a flow-through of an amount from the Alberta Electric System Operator, shown on its own line for transparency. It passes on the Balancing Pool refund or collection the distributor receives through the AESO Rider F. (from 1 January 2026) [source]
| Distributor | Filed name | Residential amount in force |
|---|---|---|
| ENMAX Power | 2026 Balancing Pool Allocation Rider | 0.1290¢ per kWh (from 1 January 2026) [source] a charge. |
| EPCOR Distribution | Rider G: Balancing Pool Rider | 0.130¢ per kWh (1 January 2026 to 31 December 2026) [source] a charge. |
| FortisAlberta | Balancing Pool Allocation Rider | 0.1198¢ per kWh (from 1 January 2026) [source] a charge. |
| ATCO Electric | Rider B: Balancing Pool Adjustment | 0.133¢ per kWh (1 January 2026 to 31 December 2026) [source] a charge. |
ENMAX files its rider as the 2026 Balancing Pool Allocation Rider and gives it no letter. FortisAlberta’s rider has no letter either. In ENMAX’s tariff, Rider F is the AESO’s ISO Consumer Allocation Rider, which is the source of the amount.
AESO Rider F applies to transmission system access under its DTS and DOS rates. This is the source of the distributor pass-through.
Transmission access charges and adjustments
A transmission access charge pays for grid access, which ENMAX calls TAC in its filed sheets. The AESO charges the distributor, which passes the cost on, while riders settle gaps between costs and collections. A later credit can return money if customers paid too much.
| Distributor | Name and letter |
|---|---|
| EPCOR Distribution | EPCOR Rider K |
| ENMAX Power | ENMAX Quarterly TAC Adjustment Rider |
| FortisAlberta | FortisAlberta QTAR |
| ATCO Electric | ATCO Electric Rider S |
FortisAlberta says its quarterly rider changes at the start of each quarter. These are the published figures for each quarter. An earlier quarter can have a different sign. A quarter with no figure shown here is not a zero.
| Distributor and filed rider | Q1, from 1 January 2026 | Q2, from 1 April 2026 | Q3, from 1 July 2026 | Q4, from 1 October 2026 |
|---|---|---|---|---|
| EPCOR Rider K | No figure shown here | No figure shown here | No figure shown here | 0.103¢ per kWh (from 1 October 2026) [source] a charge. |
| ENMAX Quarterly TAC Adjustment Rider | 0.1155¢ per kWh (1 January 2026 to 31 March 2026) [source] a charge. | -0.1396¢ per kWh (1 April 2026 to 30 June 2026) [source] a credit. | -0.1826¢ per kWh (1 July 2026 to 30 September 2026) [source] a credit. | 0.0583¢ per kWh (1 October 2026 to 31 December 2026) [source] a charge. |
| FortisAlberta QTAR | 0.0566¢ per kWh (1 January 2026 to 31 March 2026) [source] a charge. | -0.1599¢ per kWh (1 April 2026 to 30 June 2026) [source] a credit. | -0.2000¢ per kWh (1 July 2026 to 30 September 2026) [source] a credit. | 0.0155¢ per kWh (1 October 2026 to 31 December 2026) [source] a charge. |
| ATCO Electric Rider S | No figure shown here | No figure shown here | No figure shown here | 0.068¢ per kWh (1 October 2026 to 31 December 2026) [source] a charge. |
Other riders on the AUC list
The AUC list covers household riders and other charges for gas firms, producers and special sites. A letter on that list does not prove it is a separate line on your home’s bill. Some riders have ended, so match the customer class and dates to your own bill.
- ATCO Gas Rider D: Rider D accounts for gas lost on the distribution system. Its sheet applies to retailers and default supply customers using Distribution Access Service. The in-kind rate is 1.549% (1 November 2025 to 31 October 2026) [source].
- ATCO Gas Rider P: ATCO Gas Rider P applies to producers exporting gas from the distribution system. Its filed sheet is effective from 1 November 2025.
- ATCO Gas South Rider E: ATCO Gas South Rider E supplies the deemed gas value used for Calgary’s Method C franchise fee. It is a calculation basis, not a separate household line.
- Apex Rider E: Apex Rider E is a gas-loss basis used in calculating Rider G and gas deliveries. Its current sheet starts on 1 November 2026.
- Apex Rider H: Apex Rider H accounts for gas losses in settlement and balancing calculations. Its sheet applies to retailers. The in-kind rate is 0.88% (1 November 2025 to 31 October 2026) [source].
- ATCO Electric Rider E: Rider E applies to facilities covered by a customer-specific agreement. The AUC overview prints no dates for this rider tied to an agreement.
- EPCOR Rider E: EPCOR Rider E covers customer-specific facilities and is not currently in effect.
- FortisAlberta Rider E: FortisAlberta Rider E covers facilities under a customer-specific agreement. The AUC overview prints no dates for this rider tied to an agreement.
- EPCOR Rider DJ: EPCOR Rider DJ adjusts distribution costs and is not currently in effect.
- FortisAlberta’s distribution adjustment rider is not currently in effect.
These gas supply and settlement sheets do not establish whether a retailer passes them through as separate household lines.
- ATCO Electric Rider J, PBR Re-Opener, ran from 1 September 2025 to 28 February 2026. The AUC lists it as not currently in effect.
- ATCO Gas South Rider S ran from 1 September 2025 to 28 February 2026 under Decision 30140-D01-2025. The current North schedule lists no Rider S.
Direct Energy Regulated Services’ Rider C7 is printed in the retailer’s own schedule. The AUC overview marks that retailer’s riders as currently inactive. The filed schedule prints the credits below. They are already included in its net administration charge; do not add the credit twice.
| Retailer and rider | Residential credits | Period | AUC decision |
|---|---|---|---|
| Direct Energy Regulated Services, Rider C7 | Electricity Rate E1, ATCO Electric D11: C$-0.217 per day (1 July 2026 to 31 December 2026) [source], a credit. Gas Rate G1, North: C$-0.041 per day (1 July 2026 to 31 December 2026) [source], a credit. | 1 July 2026 to 31 December 2026 | 30807-D01-2026 |
This guide excludes city-owned electricity utilities in Lethbridge, Medicine Hat, Red Deer, Cardston and Ponoka, Rural Electrification Associations and gas co-ops, which set their own charges.
Find the rider and match its dates
Find the rider’s letter, the billing days and the line beside delivery, then match the rate to those dates. FortisAlberta says names on bills can differ, while the UCA says riders change each month, quarter or year. Switching the firm that sells your energy does not change these delivery riders.
FortisAlberta says each retailer may use different names for the same rider. An old bill can use an older figure. For a bill that spans a rate change, ask which consumption dates each amount covers.
Start with your electricity bill or your gas bill. For a company layout, use EPCOR, ENMAX or Direct Energy. Our high bill guide covers other causes of a larger bill.
A bill check, free during our launch
BillRobin is an Alberta service. We compare every plan we can confirm for your home, show them in order of estimated cost, and you decide. We never switch your plan, never phone you and never ask for banking details or a social insurance number.
Questions people ask
What is a rate rider on my Alberta bill?
A rate rider on an Alberta bill is a temporary credit or charge. The UCA says it recovers the actual cost of a utility service and can refund customers who were overcharged. The AUC must approve a rider before it is applied, and the amount is updated monthly, quarterly or annually. Match its dates to the days you used energy.
What is Rider T on my ATCO Gas bill?
Rider T on an ATCO Gas bill pays for gas transmission. The AUC describes it as a pass-through of NOVA Gas Transmission Ltd. charges. Your delivery area and customer class decide the rate. Look at the Low Use line for a home, then match the dates on your bill.
What is the balancing pool allocation rider?
The balancing pool allocation rider passes on a collection or refund from the AESO. The AUC says it is shown apart for clarity. EPCOR calls it Rider G and ATCO Electric calls it Rider B. Read the sign of the amount to tell a charge from a credit.
What is the transmission access charge?
A transmission access charge pays for access to the power grid. ENMAX calls this cost TAC in its filed sheets. The AESO charges the distributor, which passes the cost on. Riders settle gaps between costs and collections. A credit can return money that customers paid ahead of actual costs.
Does switching retailers change my riders?
Switching retailers leaves your delivery riders the same for the same home, use and dates. The AUC lists them by the company that delivers energy to your home. FortisAlberta says names on bills can differ, so match the letter and dates as well as the name.
Sources
Written by the BillRobin team. Updated .
Show the 37 sources
- AESO: Rider F, Balancing Pool consumer allocation rider
- Alberta Utilities Commission: Apex Utilities Inc., Appendix 1 - Rate Rider A, Franchise Tax Riders (Franchise Agreement and Rate Rider A County of Two Hills No. 21)
- Alberta Utilities Commission: Apex Utilities Inc., Appendix 1 - Rate Rider B, District & Municipal Property Tax Riders (Rate Rider B 2025 Reconciliation and 2026/2027 Calculation)
- Alberta Utilities Commission: Apex Utilities Inc., Rate Rider G Third-Party Transportation Rate Rider, effective January 1, 2026
- Alberta Utilities Commission: Apex Utilities Inc., Rate Rider H, Unaccounted-For Gas, Gas Settlement, effective November 1, 2025
- Alberta Utilities Commission: Apex Utilities Inc., Rate Rider L Load Balancing Deferral Account Rider, effective May 1, 2025 to October 31, 2026
- Alberta Utilities Commission: ATCO Electric Ltd., Appendix 1 - Rider A municipal assessment, Rider A Municipal Assessment Surcharge, Table 1: Total Rider A (effective 2026 04 01)
- Alberta Utilities Commission: ATCO Electric Ltd., Appendix 3 - 2026 interim price schedules, effective January 1, 2026
- Alberta Utilities Commission: ATCO Electric Ltd., Quarterly AESO DTS Deferral Account Rider S Application - Q4 2026, effective October 1, 2026
- Alberta Utilities Commission: ATCO Electric Ltd., Rider G Temporary Adjustment, effective January 1, 2026 to December 31, 2026
- Alberta Utilities Commission: ATCO Gas and Pipelines Ltd., Appendix 1 - South Rate Rider B, Municipal Property Tax and Specific Costs (South Rate Rider B 2025 Reconciliation and 2026 Calculation), effective February 1, 2026
- Alberta Utilities Commission: ATCO Gas and Pipelines Ltd., Appendix 2 - North Rider A, Municipal Franchise Fee (Franchise Agreement and Rate Rider A with the Village of Edgerton), effective October 1, 2026
- Alberta Utilities Commission: ATCO Gas and Pipelines Ltd., Appendix 2 - North Rider B, Municipal Property Tax and Specific Costs (North Rider A and North Rider B Rate Schedule Updates), effective July 1, 2026
- Alberta Utilities Commission: ATCO Gas and Pipelines Ltd., Appendix 2 - Rate Rider A, South Rider "A" Municipal Franchise Fee (Franchise Agreement and Rate Rider A with the Town of Picture Butte), effective September 1, 2026
- Alberta Utilities Commission: ATCO Gas and Pipelines Ltd., Appendix 3 - Rider D, 2025 Unaccounted-For Gas Rider D and Rider P, Rider D effective November 1, 2025 (Decision 30255-D01-2025)
- Alberta Utilities Commission: ATCO Gas and Pipelines Ltd., ATCO Gas South Transmission Service Charge (Rider T) Rate Schedule, January 1, 2026
- Alberta Utilities Commission: ATCO Gas and Pipelines Ltd., South Rider "L" to all rates for crediting or debiting Load Balancing Deferral Account balances, effective May 1, 2026
- Alberta Utilities Commission: ATCO Gas and Pipelines Ltd., South Rider "W" Weather Deferral Account Rider, effective September 1, 2026
- Alberta Utilities Commission: AUC Disposition 31030-D01-2026 (September 11, 2026), Appendix 1 - FortisAlberta Inc. 2026 Q4 QTAR filing, Rider Schedules (Quarterly Transmission Adjustment Rider)
- Alberta Utilities Commission: AUC Disposition 31032-D01-2026 (September 11, 2026), Appendix 1 - EPCOR Distribution & Transmission Inc. Rider K, Transmission Charge Deferral Account True-Up Rider (Short-Term Adjustment, effective October 1, 2026)
- Alberta Utilities Commission: Direct Energy Regulated Services, 2026 Final Rate Schedules for DRT Service in ATCO Gas North Service Territory, effective July 1, 2026
- Alberta Utilities Commission: Direct Energy Regulated Services, 2026 Final Rate Schedules for Electricity RRT Service, effective July 1, 2026
- Alberta Utilities Commission: ENMAX Power Corporation, Appendix 3 - 2026 interim rate schedule, rates in effect as of January 1, 2026
- Alberta Utilities Commission: ENMAX Power Corporation, Quarterly Transmission Access Charge ("TAC") Adjustment Rider, effective October 1, 2026
- Alberta Utilities Commission: ENMAX Power Corporation, Rider F, 2026 Balancing Pool Allocation Rider, effective January 1, 2026
- Alberta Utilities Commission: EPCOR Distribution & Transmission Inc., Appendix 10 - Rider J, SAS True-Up Rider (Interim Adjustment, effective January 1, 2026)
- Alberta Utilities Commission: EPCOR Distribution & Transmission Inc., Appendix 9 - 2026 Balancing Pool Rider G (Temporary Adjustment, effective January 1, 2026)
- Alberta Utilities Commission: FortisAlberta Inc., 2026 Annual Performance-Based Regulation Rate Adjustment, Appendix 3 - 2026 interim rate schedule (Interim Rates, Options and Riders Schedules, January 1, 2026)
- Alberta Utilities Commission: FortisAlberta Inc., Appendix 1 - Municipal Assessment Rider A-1, 2026 Rate Sheets (Rider A-1 effective July 1, 2026)
- Alberta Utilities Commission: FortisAlberta Inc., Appendix 1 - Municipal franchise fee riders (Rates, Options and Riders Schedules, effective May 1, 2026)
- Alberta Utilities Commission: Rate riders
- ATCO Gas: North rate schedule
- ATCO Gas: South rate schedule, Rider S
- The City of Calgary, Energy costs page
- EPCOR Distribution & Transmission Inc., Schedule - Franchise Fee Rates (Local Access Fee), effective January 1, 2026
- FortisAlberta: Bill terminology
- Utilities Consumer Advocate: Rate riders
https://billrobin.com/ca/en/alberta/energy/rate-riders?utm_medium=share&utm_source=page
Are you on the right energy plan?
Send your bills as PDFs. We compare the plans available at your address, and you decide. Free during our launch.
Check my bills, free- We never phone you
- We never switch your plan. You decide.