Show all 4 key facts
  • Delivery charges on the bill: The delivery portion of the utility bill is where consumers can see distribution and transmission charges, any applicable Municipal Franchise Fees or Local Access Fees, and rate riders.

    read 15 October 2026

    Alberta distribution companies.

    Source: Utilities Consumer Advocate: Distributor details

FortisAlberta and ATCO Electric own the local wires. They bill your retailer, which passes the regulated charges to you. The AUC approves rates; the UCA explains delivery. You pay daily charges, distribution and transmission per kWh, riders and town fees. You cannot choose the wires company. Switching retailers leaves these rates unchanged.

Your retailer collects the delivery charges

Your retailer collects the delivery charges for the wires at home. ATCO Electric’s terms say it bills the retailer. FortisAlberta’s sample bill shows these costs apart from the power you buy. The bill comes from your retailer. You still pay for the same wires when you choose a new plan.

ATCO Electric bills the retailer for electric distribution services. Its retailer terms also allow it to bill a customer directly for some amounts under the customer terms. (read 30 October 2026) [source]

The default electricity retailer in the EPCOR Distribution (Edmonton) and FortisAlberta areas is EPCOR. (read 15 October 2026) [source] The default electricity retailer in the ATCO Electric area is Direct Energy Regulated Services. It is also the default natural gas retailer for ATCO Gas. (read 15 October 2026) [source]

The lines in FortisAlberta Rate 11

FortisAlberta’s home rate has a daily charge and charges for each kWh you use. Its schedule calls them facilities and service, system usage and transmission. Riders adjust those charges, and town fees add local costs. The AUC approves the schedule. Your retailer may group several lines under one bill heading.

Rate 11 has no demand charge. The daily facilities and service charge is also its distribution minimum charge. (read 30 October 2026) [source] FortisAlberta says retailers may use different names for riders. (read 30 October 2026) [source]

The bill wording below comes from FortisAlberta’s sample and terminology guide. A bill category can cover several tariff lines. Rider A-1 passes on a property tax set in part by the local taxation authority. (read 30 October 2026) [source]

FortisAlberta Rate 11, with Airdrie town fees. Rates in force on 31 October 2026.
As the tariff files itPublished bill wordingWhat it pays forDoes it change with useAmount
Facilities and Service ChargeDistribution charge - service provided by FortisAlbertaKeeps the local connection readyNo, per dayC$1.034442 per day
System Usage ChargeDistribution charge - service provided by FortisAlbertaBuilds, runs and maintains the local wiresYes, per kWh3.3477¢ per kWh
Variable Charge (Transmission Charges)Transmission chargeMoves power through the high-voltage gridYes, per kWh4.2560¢ per kWh
Balancing Pool Allocation RiderRate RidersPasses on the Balancing Pool allocationYes, per kWh0.1198¢ per kWh
Quarterly Transmission Adjustment RiderRate RidersAdjusts transmission costs each quarterYes, per kWh0.0155¢ per kWh
Base Transmission Adjustment RiderCheck your retailer’s wordingA credit on the base transmission chargeYes, with transmission use-0.59%
Rider A-1 Municipal Assessment RiderA-1 Municipal Assessment RiderPasses on local property taxPartly, a percentage1.04%
Municipal Franchise Fee RiderLocal access feePays the town for the right to use its landPartly, a percentage20%

Bill wording: Understanding your bill: sample bill; Bill terminology explanation.

Tariffs and town fees: FortisAlberta Inc., 2026 Annual Performance-Based Regulation Rate Adjustment, Appendix 3 - 2026 interim rate schedule (Interim Rates, Options and Riders Schedules, January 1, 2026); AUC Disposition 31030-D01-2026 (September 11, 2026), Appendix 1 - FortisAlberta Inc. 2026 Q4 QTAR filing, Rider Schedules (Quarterly Transmission Adjustment Rider); FortisAlberta Inc., Appendix 1 - Municipal Assessment Rider A-1, 2026 Rate Sheets (Rider A-1 effective July 1, 2026); FortisAlberta Inc., Appendix 1 - Municipal franchise fee riders (Rates, Options and Riders Schedules, effective May 1, 2026).

Find the figures and towns on the FortisAlberta distributor page. Read the guide to delivery and riders for the wider picture.

The lines in ATCO Electric D11

ATCO Electric’s home schedule splits delivery into daily charges, use charges and riders. The distribution and service lines each have a daily part. Distribution and transmission also charge for each kWh. The AUC approves these interim home rates. Your retailer’s bill may group them under broader delivery headings.

D11 has no demand charge. The AUC approves these interim 2026 rates. Distribution and service have daily customer charges. Distribution and transmission have energy charges per kWh. (read 30 October 2026) [source]

The bill categories below come from a retailer’s published bill guide. They are broad categories, not a promise of your bill’s exact wording. ATCO Electric’s municipal assessment rider includes franchise fees and property taxes. (read 30 October 2026) [source]

ATCO Electric D11, with Grande Prairie town fees. Rates in force on 31 October 2026.
As the tariff files itPublished bill wordingWhat it pays forDoes it change with useAmount
Customer Charge: DistributionDistribution & delivery chargesKeeps the local connection readyNo, per dayC$1.4125 per day
Customer Charge: ServiceCheck your retailer’s wordingThe schedule’s separate daily service amountNo, per dayC$0.2698 per day
Energy Charge: DistributionDistribution & delivery chargesBuilds, runs and maintains the local wiresYes, per kWh9.03¢ per kWh
Energy Charge: TransmissionTransmission chargesMoves power through the high-voltage gridYes, per kWh4.79¢ per kWh
Municipal Assessment (Rider A)Municipal franchise / local access feesPasses on property tax and franchise feesPartly, a percentage12.26%
Balancing Pool Adjustment (Rider B)Rate riders & government feesPasses on the Balancing Pool adjustmentYes, per kWh0.133¢ per kWh
Temporary Adjustment (Rider G)Rate riders & government feesA temporary creditYes, per kWh-0.212¢ per kWh
SAS Adjustment (Rider S)Rate riders & government feesAdjusts system access costs each quarterYes, per kWh0.068¢ per kWh

Bill wording: Understanding your energy bill.

Tariffs and town fees: ATCO Electric Ltd., Appendix 3 - 2026 interim price schedules, effective January 1, 2026; ATCO Electric Ltd., Appendix 1 - Rider A municipal assessment, Rider A Municipal Assessment Surcharge, Table 1: Total Rider A (effective 2026 04 01); ATCO Electric Ltd., Rider G Temporary Adjustment, effective January 1, 2026 to December 31, 2026; ATCO Electric Ltd., Quarterly AESO DTS Deferral Account Rider S Application - Q4 2026, effective October 1, 2026.

D11 TOTAL PRICE, before riders and town fees: C$1.6823 /day and 13.82 ¢/kW.h. These are delivery rates, not the price of the power you buy. D11 schedule.

D13 time of use is available by request only, at the company’s discretion, with an advanced meter. On peak runs from 4 p.m. to 9 p.m. (read 30 October 2026) [source] ATCO Electric’s PBR Re-Opener Refund, Rider J, ended on 28 February 2026. (read 30 October 2026) [source]

Find the figures and towns on the ATCO Electric distributor page.

A worked month in each town

FortisAlberta and ATCO Electric file different rates with the AUC. The two examples below use the same amount of power and the same number of days. Each shows daily charges, use charges, riders and town fees. These towns are two examples of the tariffs, with no ranking of households.

Rates and riders change, including by quarter. These examples use the rates in force on the date shown. Delivery is the same whichever retailer you pick. The energy part uses each area’s default seller. Your plan may have a different energy price and retailer charge.

The Airdrie example includes the small base transmission credit.

For illustration

Airdrie: FortisAlberta Rate 11

Rates in force on 31 October 2026. For 600 kWh and 365/12 days, about 30.42 days.

Airdrie delivery and energy, kept apart
LineAmount
Facilities and Service Charge: C$1.034442 per day (from 1 January 2026) [source]C$31.46
System Usage Charge: 3.3477¢ per kWh (from 1 January 2026) [source]C$20.09
Variable Charge (Transmission Charges): 4.2560¢ per kWh (from 1 January 2026) [source]C$25.54
Balancing Pool Allocation Rider: 0.1198¢ per kWh (from 1 January 2026) [source]C$0.72
Quarterly Transmission Adjustment Rider: 0.0155¢ per kWh (1 October 2026 to 31 December 2026) [source]C$0.09
Base Transmission Adjustment Rider credit: -0.59% (from 1 January 2026) [source]-C$0.15
Rider A-1 Municipal Assessment Rider: 1.04% (from 1 July 2026) [source]C$0.80
Municipal Franchise Fee Rider: 20% (from 1 April 2021) [source]C$15.42
Delivery including riders and town fees, before GSTC$93.97
GST on deliveryC$4.70
Delivery including GSTC$98.66
Town fees including GST, already included aboveC$17.03
Default energy, before GST: 12.01¢ per kWh (1 January 2025 to 31 December 2026) [source]C$72.06
Default retailer’s charge, before GST: C$0.260 per day (from 1 July 2026) [source]C$7.91
GST on energy and the retailer’s chargeC$4.00
Energy and retailer’s charge including GSTC$83.97

For illustration

Grande Prairie: ATCO Electric D11

Rates in force on 31 October 2026. For 600 kWh and 365/12 days, about 30.42 days.

Grande Prairie delivery and energy, kept apart
LineAmount
Customer Charge: Distribution: C$1.4125 per day (from 1 January 2026) [source]C$42.96
Customer Charge: Service: C$0.2698 per day (from 1 January 2026) [source]C$8.21
Energy Charge: Distribution: 9.03¢ per kWh (from 1 January 2026) [source]C$54.18
Energy Charge: Transmission: 4.79¢ per kWh (from 1 January 2026) [source]C$28.74
Municipal Assessment (Rider A): 12.26% (from 1 April 2026) [source]C$16.44
Balancing Pool Adjustment (Rider B): 0.133¢ per kWh (1 January 2026 to 31 December 2026) [source]C$0.80
Temporary Adjustment (Rider G) credit: -0.212¢ per kWh (1 January 2026 to 31 December 2026) [source]-C$1.27
SAS Adjustment (Rider S): 0.068¢ per kWh (1 October 2026 to 31 December 2026) [source]C$0.41
Delivery including riders and town fees, before GSTC$150.46
GST on deliveryC$7.52
Delivery including GSTC$157.99
Town fees including GST, already included aboveC$17.26
Default energy, before GST: 12.02¢ per kWh (1 January 2025 to 31 December 2026) [source]C$72.12
Default retailer’s charge, before GST: C$0.558 per day (1 July 2026 to 31 December 2026) [source]C$16.97
GST on energy and the retailer’s chargeC$4.45
Energy and retailer’s charge including GSTC$93.55

Read the local pages for Airdrie and Grande Prairie. Town fees are explained in local access and franchise fees.

Rural homes share longer lines

Rural delivery costs more because homes are far apart. The Utilities Consumer Advocate points to low population density and longer distances between sites. More wires serve fewer homes, so each home bears more of the network cost. Switching retailers leaves that network and its regulated delivery rates the same.

The UCA describes “low population density and longer distances between consumer sites”. Distribution charges are higher in rural Alberta than in urban areas because of low population density and longer distances between customer sites. (from 1 January 2026) [source]

These are the UCA’s historic figures, not the current tariff examples above. In 2025, for 600 kWh, monthly distribution charges ranged from $31.55 (in EPCOR's service area) to $97.89 (in ATCO’s service area), according to the Utilities Consumer Advocate. (1 January 2025 to 31 December 2025) [source] In 2025, for 600 kWh, monthly transmission charges ranged from $23.93 (in ENMAX's service area) to $26.32 (in ATCO Electric's service area), according to the Utilities Consumer Advocate. (1 January 2025 to 31 December 2025) [source]

The examples also reflect different distribution tariffs. FortisAlberta’s daily line is C$1.034442 per day (from 1 January 2026) [source] and its use line is 3.3477¢ per kWh (from 1 January 2026) [source]. ATCO Electric’s daily distribution line is C$1.4125 per day (from 1 January 2026) [source], plus service of C$0.2698 per day (from 1 January 2026) [source]. Its distribution use line is 9.03¢ per kWh (from 1 January 2026) [source].

Read how transmission, distribution and riders fit together.

Using less lowers the lines charged per kWh

Using less power lowers the lines charged per kWh. The daily lines stay due for each day of service. The Rate 11 and D11 schedules list these daily charges and charges based on use. A retailer switch changes none of these delivery rates. Your power use still affects the total.

ATCO Electric’s time of use option is available by request. Whether it costs less depends on when you use power. Ask your retailer to explain a disputed line. Read who to contact about an energy bill complaint if it remains unresolved.

Read about fixed charges and a high utility bill.

A bill check, free during our launch

BillRobin is an Alberta service. We compare every plan we can confirm for your home, show them in order of estimated cost, and you decide. We never switch your plan, never phone you and never ask for banking details or a social insurance number.

Send us your gas and electricity bills as PDFs. No PDF? Screenshots or a photo work too. We compare the plans at your address, free during our launch period.

Questions people ask

What is the distribution charge on my ATCO Electric bill?

The distribution charge on an ATCO Electric bill pays for the local wires that bring power to your home. The Utilities Consumer Advocate explains that role. ATCO Electric lists both a daily charge and a charge based on use. Your retailer collects them on your bill.

Why is there a FortisAlberta charge on my EPCOR bill?

A FortisAlberta charge on your EPCOR bill pays for the wires at home. The sample bill splits those costs from the power you buy. EPCOR is the default seller in this area. You can choose a new plan. The same wires and rates still serve your home.

Is there a demand charge on a home electricity bill in Alberta?

FortisAlberta Rate 11 and ATCO Electric D11 list no demand charge. Their home rate schedules charge by the day and by the power used. This statement covers those two rates only. The AUC approves the schedules. Other rate classes can have different terms and charges.

Do FortisAlberta and ATCO Electric bill me directly?

FortisAlberta and ATCO Electric charges come through your retailer’s bill. ATCO Electric’s terms say it bills the retailer for the wires. It may also bill a customer directly for some amounts. That is a separate rule. It does not mean the company sends your monthly bill.

Why are my delivery charges higher in the country?

Delivery charges are higher in the country because homes are far apart. The UCA says low population density and long lines raise costs. More wires serve fewer homes. Each home pays a share of those costs. A new plan leaves the same wires and delivery rates in place.

Sources

Written by the BillRobin team. Updated .

Show the 11 sources
Report a mistake

Are you on the right energy plan?

Send your bills as PDFs. We compare the plans available at your address, and you decide. Free during our launch.

Check my bills, free
  • We never phone you
  • We never switch your plan. You decide.